Logtown Fire Safe Council
Notes of the January 12, 2008 meeting
6109 Quartz Drive, station 44
Diamond Springs - El Dorado Fire Protection District
DOWNLOAD NOTES IN PDF FORMAT
Ken Hasse called the meeting to order at 9:05 AM. The attendance sheet was passed around for initials.
Announcements: The EDFSC "Gathering of the Councils" will be held at the
Diamond Springs Firefighters Hall at 1:00 PM, Wednesday January 23rd. All are
welcome to attend.
Projects: The following 2008 projects were established at a recent Logtown FSC
Executive Board meeting.
- Acommunity wide green waste cleanup will be scheduled for sometime in May.
At least four dumpsters will be available at locations on Quartz, Dolomite and
two on Crystal Blvd. We will attempt to schedule chipping first to reduce the
amount of waste in the dumpsters. Flyers will be distributed for sign-up &
scheduling.
- The Fire Safe Council plans to place Fire Safety billboards at four locations
that will be visible to most of the residents within the Logtown area. Proposed
locations are Quartz/Crystal, Dolomite/Monitor, Union Mine/Maric/Church
Mine junctions and the north end of Dolomite. The message will be "It's Your
Responsibility" for defensible space and road frontage cleanup. Permission to
use the easement areas will be required. Permission to use the Diamond Springs
– El Dorado FPD, Calfire and the EDFSC logos will also be required. Red Flag
warning may be incorporated with the billboards.
- The Logtown FSC will resume training for an inspection team and will offer
defensible space "pre"-inspections on an as requested basis. Inspections
results will only be forwarded to Calfire if defensible space requirements are
met thus helping Calfire satisfy their "quotas".
Hydrant Checks - Rich Englefield
Hydrant inspections will resume at the South end of Crystal.
An e-mail from EID staff indicated that some hydrants have been repaired or
replaced this past year but that others would not be replaced because existing
working hydrants met the 1000 feet spacing requirements. The information will be
forwarded to Erik Peterson for follow-up. There are eight non-working hydrants in
the Quartz/Stope area. The Fire Safe Council will send a letter to George
Osborne requesting repair or replacement of these hydrants. Residents were
encouraged to e-mail George Osborne, gwclosborne@comcast.net or to attend an EID
board meeting to express their concern.
CWPP Follow-Up
There will be a meeting with Calfire, Diamond Springs-El Dorado FPD, BLM and El
Dorado RCD personnel to discuss projects identified in the Logtown CWPP. The
group will also tour the proposed work areas. The prospect for obtaining funding
for some of this work is very good.
EDCFSC (El Dorado County Fire Safe Council) Update -Vicki Yorty
Five proposals for Title 3 funding have been submitted: FSC Operations Budget,
Defensible Space Visits & Education, Public Education, Community Clean-Up &
Green Waste Dumpsters and Red Flag Project. The Community Clean-Up request
was for considerably more than last year. This is a popular program & funds are
used up fast. A dumpster costs about $300 - $400. Funding for the chipping will
be available in the next couple of months.
Request for funding for CWPPs for Placerville and Pollock Pines have also been
submitted.
Neighborhood Coordinator Update
A major emphasis in the neighborhoods this year will be on maintaining and
improving the phone trees. Pat Dwyer suggested that phone trees could be used
(and tested) along with the flyers as a means of spreading information on the
community clean-up program.
Prospects for completing a phone tree in the South Crystal Blvd. Area (Black Zone)
are good with increased interest and new volunteers. We still need someone from
the Monitor area to work on a phone tree there.
We will be able to get fire alerts directly from Calfire's alpha system this year.
Work has been done to provide a fire truck turn around at the end of Maric Road.
It will be completed with gravel in the spring.
There was some discussion about possible evacuation routes between Maric and
Dolomite and from the north end of Quartz.
Mike Veimoen asked about the EID water line and a fire hydrant near the end of
Oak Ridge North. A request would have to be submitted to EID and there would
be significant cost.
Adjourn: The meeting was adjourned at about 9:50 AM. The next meeting will be
February 9, 2008.
|